The short answer

When a Kerala panchayat buys solar street lights through ANERT, the tender is open only to agencies that ANERT has empanelled, and the lights must meet ANERT's technical specification. So the first two questions for any panchayat or supplier are: is the agency on ANERT's current empanelment list, and which ANERT model does the tender ask for?

This guide explains how the process works, using a 2024 ANERT tender for 20W (Model-C) solar street lights at a Grama Panchayath in Idukki as the example. Tender terms change from year to year, so always read the current tender document before you act.

How the process works

ANERT's orders say that local self-government institutions should invite tenders from the agencies ANERT has empanelled for solar street lighting. ANERT publishes the list of empanelled agencies and the technical specifications. Tenders are published on the Kerala e-tenders portal (etenders.kerala.gov.in), and bids are submitted online.

Who can bid

In the 2024 tender we reviewed, a bidder had to:

  • Be empanelled with ANERT for solar street and flood lighting for that year, and quote the empanelment number in the bid
  • Have at least one service centre or authorised service provider in Kerala
  • Hold a Class III (or higher) Digital Signature Certificate
  • Register on the Kerala e-tenders portal
  • Submit only one bid

Manual bids were not accepted. The bid had to be submitted online and "frozen" before the deadline, and bidders were advised to submit at least two working days early.

What the specification asks for (20W Model-C example)

ANERT uses numbered models (for example Model-A at 14W and Model-C at 20W). In the 2024 Model-C tender the specification included:

  • LED luminaire: 20W, about 3,000 lumens, white light at 5000–6500K, IP66 enclosure, with LM-79 and LM-80 test reports
  • Solar module: 100Wp crystalline silicon, certified to IEC 61215, 61730 and 61701 (or BIS equivalent)
  • Battery: lithium iron phosphate (LiFePO4), 538 Wh, IEC 62133 certified, in an IP66 box mounted at least 3 m high
  • Autonomy: 24 hours
  • Electronics: MPPT charge controller, at least 90% efficiency, 50% dimming from midnight to 4 AM
  • Pole: 6 m hot-dip galvanised pole with an M25 concrete foundation
  • Warranty: 5 years for the complete system from commissioning, with the solar module delivering at least 90% output at 10 years and 80% at 25 years

Compare this with a commercial light. A light that is good for an estate or a factory yard is not automatically the same as an ANERT model, and the other way round.

Delivery and installation terms

  • Materials delivered within 21 days and installation finished within 30 days of the work order
  • Installation spots fixed in a joint site visit with ANERT
  • A name plate fixed on the pole, plus quality stickers
  • Insurance for the system from dispatch until five years after commissioning, paid by the bidder
  • An operation and maintenance manual in English and Malayalam
  • A delay penalty of 0.5% per week, capped at 10%

Payment terms in that tender

  • No advance payment
  • 90% of the contract value paid on completion, against the invoice and a district-certified completion report
  • The remaining 10% held as performance security and released in yearly instalments over five years, or replaced by a five-year bank guarantee
  • Prices fixed and inclusive of GST, transport, installation and commissioning

These terms affect a supplier's cash flow. Small agencies should plan for them before bidding.

A checklist for panchayat secretaries

  • Is the supplier on ANERT's current empanelment list, and for which models?
  • Does the supplier have a service centre in Kerala?
  • Does the offered product match the ANERT specification, with test reports and certificates?
  • What warranty and insurance does the tender require, and will the supplier honour them?
  • Who will maintain the lights after commissioning, and how quickly can a fault be fixed?
  • Are the pole positions agreed on site, so lights are not under trees or in shade?

Common problems on panchayat projects

  • Lights installed under trees, so the panel cannot charge the battery
  • Foundations not cured long enough, so poles lean after the monsoon
  • No clear person responsible for maintenance after the warranty period starts
  • Poles spaced for convenience, not for even light on the road

For why curing time, pole spacing and shade matter, see our guides on installation in Kerala and on sizing a solar street light for your road.

Where FRK Lighting fits

FRK Lighting supplies and installs solar street lights for estates, campuses, factories, car parks, resorts and other private and institutional sites across Kerala. For panchayat projects that go through ANERT tenders, the supplier must be on ANERT's empanelment list, so please check the list before you invite bids. If your project is outside that route, send us your location and requirement and we will arrange a free site assessment.

Call or WhatsApp: +91 70258 88461

Frequently asked questions

Who can bid for ANERT solar street light tenders?

Agencies that ANERT has empanelled for solar street lighting, with a Class III Digital Signature Certificate, registration on the Kerala e-tenders portal and a service centre in Kerala. Check the current tender for the exact conditions.

Where are the tenders published?

On the Kerala e-tenders portal (etenders.kerala.gov.in). ANERT also lists tenders and empanelled agencies on its website.

How long is the warranty on ANERT solar street lights?

In the 2024 tender we reviewed, the warranty was five years for the complete system from commissioning. Check the current tender for the present terms.

How long does installation take under an ANERT tender?

In that tender, materials were due within 21 days and installation within 30 days of the work order.

Do these terms apply to every project?

No. Specifications, quantities and conditions differ between tenders and years. Always read the tender document for the project you are bidding for or approving.

Tell us about your location and requirements. Our team will help you find a suitable Solar Lighting

Chat on WhatsApp